Board of Commissioners Friday Update
August 15, 2008
ITEM 1. PUBLIC WORKS DIRECTOR SEARCH
Public Works Director interviews were conducted this week. There is nothing else to report at this time about the selection of a Public Works Director.
ITEM 2. DROUGHT UPDATE
According to an August 14th News & Observer article, “Drought conditions persist particularly in parched western North Carolina, but more local governments are conserving water than a year ago…. Of the 660 public water systems in the state, 54 percent had water restrictions in place as of July… A year ago, only 12 percent of the systems had conservation measures in place”.
Moderate drought conditions prevail in the Triangle.
Falls Lake, which supplies water for most of Raleigh and Wake County, was about 2.5 feet higher than a year ago, and 90 percent of its water supply remains.
You can read the entire News & Observer article here.
ITEM 3. ELECTED OFFICIALS INVITED TO PLANNING BOARD AND BOARD OF ADJUSTMENT TRAINING
Please remember that elected officials are invited to attend some upcoming Board of Adjustment and Planning Board training events. Elected officials are asked to let staff know in advance if they wish to participate. Zachry Nichols of the NC Department of Commerce will be hosting these training sessions, which will be held on the following dates:
· Planning Board Citizen Training - October 9th at 7:00 PM
· Board of Adjustment Citizen Training - October 23rd at 7:00 PM
Both training sessions will be held in the Wendell Courtroom.
ITEM 4. DOT PROJECT AT 97 / 64 BUSINESS INTERCHANGE
As you are aware from last week’s Friday Memo, the NC Department of Transportation is planning to make changes to the NC 97 / US 64 Business interchange and is asking the town board for a resolution of support for this project.
A digital copy of the plans was received this week, but it is too large to be distributed via email. A copy of the plans will be included in the August 25th agenda packet, along with a resolution of support for the board’s consideration.
The project is expected to cost about $685,000.
ITEM 5. FOLLOW-UP ON CABLE SERVICE TO THE COMMUNITY CENTER
As a follow-up to the July 28th Board of Commissioners meeting (at which time the extension of cable service to the Wendell Community Center was discussed), Recreation Director Brinkley Wagstaff met with representatives of Time Warner Cable on Monday, August 11th concerning the town’s desire for a service line to the community center. Time Warner Cable staff plans to bring a revised proposal for the line installation back to the town in the near future.
ITEM 6. ONLINE AUCTION
As you are aware, the town is currently selling surplus items on the GovDeals web site. To view the items, check-out www.govdeals.comm, select “North Carolina” and “Wendell” on the drop-down menus, and conduct a search. The online auction of some items has already closed, and staff is pleased with the results.
ITEM 7. HANOR LANE SCHEDULE
A rough schedule for the Hanor Lane sewer project is as follows:
August 5-8: Mobilize, Stake, Erosion Control, Materials Delivered
August 11-15: Prepare for bore across Wendell Blvd, additional materials Delivered.
August 18-22: Bore made across Wendell Blvd. Begin laying pipe by the Dollar General and set manholes. Install Water Service for Dollar General
August 25 – 29: Prepare for additional bores, continue laying pipe by the Dollar General and set manholes.
September 1-5: Continue laying pipe by the Dollar General and set manholes.
September 8-12 Continue laying pipe by the Dollar General and set manholes.
September 15-19 Continue laying pipe by the Dollar General and set manholes and begin laying pipe near apartment buildings. (Install Sewer Service for Dollar General)
September 22 – 26 Prepare for bores along Hanor Lane and Marshburn Road continue laying pipe
September 29 – October 3: Bore under Hanor Lane and Marshburn Road continue laying pipe near apartments
October 6 – 10: Lay pipe near apartments and search for services that are on the line near Hanor Lane.
October 13-17 Continue laying pipe on Hanor Lane and Marshburn Road and Prepare the abandon the line on Hanor Lane.
October 20-24 Vacuum test manholes, any line testing left to complete, check seed and straw complete or reseed any that needs to be reseeded.
October 27-28: Clean up Job Site
October 28 – November 12: Complete testing, Remove Silt Fence and Erosion Control Devices.
ITEM 8. OTHER:
A. Wake County Commissioner Lindy Brown has asked to talk to the Board of Commissioners at its September 22nd meeting concerning the issue of affordable housing.
B. The portion of Martin Pond Road that closed on April 14th for the Wendell Falls construction is now scheduled to re-open around the middle of September (one month later than originally discussed).
ITEM 9. UPCOMING EVENTS:
April 2007 May 2007 June 2007 July 2007 August 2007 October 2007 November 2007 December 2007 January 2008 February 2008 March 2008 April 2008 May 2008 June 2008 July 2008 August 2008 September 2008 October 2008 November 2008 December 2008 January 2009 February 2009 March 2009 April 2009 May 2009 June 2009 July 2009 August 2009 September 2009 October 2009 November 2009 December 2009 January 2010 February 2010 March 2010 April 2010 May 2010 June 2010 July 2010 August 2010 September 2010 October 2010 November 2010 December 2010 January 2011 February 2011 March 2011 April 2011 May 2011 June 2011 July 2011 August 2011